Dark Tub to Bright Shower

Project Goals:

  • Remove the existing bathtub and replace with a walk-in shower.  Remove hard to reach cabinets above tub to improve shower space.
  • Update the bathroom with new painted cabinets, quartz countertop, and updated fixtures.
  • Remove tile floor and replace with luxury vinyl tile flooring.

Project Cost Category: Bathroom Midrange Economy

Project Overview

After completing their kitchen remodel a few years ago, this homeowner was ready to have the bathroom updated and wanted to make sure to work with Jaime again to achieve her design goals. The existing bathroom felt more cramped due to some strange storage above the shower. The goal was to open things up a bit and make it easier to maintain. Pull and replace remodel of an existing bathroom in Williamston, Michigan. The tub/shower combo was removed and replaced with a cultured stone shower with bench and shower niche. The vanity cabinet, above commode storage cabinet, and linen cabinet were replaced with semi-custom updated cabinets from Pioneer Cabinetry. The vinyl flooring was removed and replace with an updated vinyl floor with an updated pattern. The bathroom walls were patched and painted and new bathroom accessories were installed along with updated lighting, ceiling fan, and mirror.

Project Foreman

Christopher Hicks

Project Designer

Jaime Dunn

Project Gallery

Design Concepts

Project Timeline

Project Development Start

June 8, 2023

Production Start

October 16, 2023

Project Completion

January 19, 2024