"Make It Not Gross!"
Project Goals:
- Update the shower to “make it not gross” (customer request!).
- Patch drywall in adjacent spaces.
- Update the basement laundry to also make that area not gross (customer’s words, not ours!)
- Update flooring and lighting.
Project Cost Category: Bathroom Refresh
Project Overview
This basement update included an update to portions of the basement bathroom with a complete remodel of the shower area to increase the size of the shower which had an impact on the adjacent bedroom. The flooring throughout a large portion of the basement was updated, specifically in the updated bathroom and basement laundry room. We completed various drywall patches and repair and uncovered areas of leaking from the exterior that was remedied. The tile shower was a big focal point of the bathroom remodel with a beautiful white subway tile with herringbone pattern tile niche and glass block integrated to brighten the space.
Project Foreman
Christopher Hicks
Project Designer
Mark Dixon
Design Concepts


Project Timeline
Project Development Start
July 31, 2024
Production Start
October 24, 2024
Project Completion
February 19, 2025
While the majority of the project was completed earlier, small portions had to wait to be completed due to winter conditions.